Significant Southwest Crestview Bypass Bridge Construction Milestone
2024-12-09
According to Okaloosa County Public Works Director Jason Autrey, construction on the Southwest Crestview Bypass has achieved a significant milestone. The installation of bridge infrastructure spanning railroad tracks is a major step forward in this project.
Witness the Progress of Southwest Crestview Bypass Construction
Bridge Construction Details
The bridge construction showcases an impressive feat with 370 piles spread across 14 bents. These bents form the solid foundation for the columns and caps that will support the deck. Currently, bridge decking is already in place on certain portions of the structure, patiently awaiting the completion of concrete pouring and surface treatment. As Autrey mentioned during a project update video from the county, "The bridge is the long-lead work item. We still have a little under a year to go on this."This extensive bridge construction is a crucial part of the overall project. It not only enhances the infrastructure but also plays a vital role in connecting different sections. The 370 support piles are a testament to the engineering prowess involved. When completed within the year, it will help seamlessly connect the newly paved north-south section, improving traffic flow and safety.Multiple Components of the Project
The project encompasses a wide range of components. Along with the bridge construction, asphalt is being installed on the north-south portion and the western side of Fallen Heroes Way near Antioch Road. On the eastern side near Highway 85, additional road work is progressing smoothly, with stormwater features being installed. This comprehensive approach ensures that the entire bypass area is being developed in a coordinated manner.All four lanes of PJ Adams Parkway are now open to traffic, which has already started to improve the flow and safety of the area. The Florida Department of Transportation is also actively working on the interchange at I-10 and PJ Adams, further enhancing the connectivity of the region.New K-8 School Construction Along the Route
A new K-8 school is taking shape along the route. The county is collaborating closely with the school board to establish access to the parcel. The new 1,200-student facility, set to open in August 2026, will be constructed on 49 acres of an 80-acre parcel west of the new Crestview bypass. This marks a significant milestone as it is the district's first new school construction since 2007-2008.Pineview School, as it has been recently named, is a two-story school that will boast various amenities. It will have classroom wings, a gymnasium, band and chorus rooms, a media center, and a cafeteria designed as an Enhanced Hurricane Protection Area. This school is specifically designed to address the overcrowding issues in the area's elementary and middle schools, providing a much-needed educational space for the students.Project Funding and Sources
The 13.5-mile project includes the bypass, east-west connector, and PJ Adams Parkway improvements. Funding for this extensive project comes from multiple sources. Voter-approved surtax revenue plays a crucial role, supported by the Florida Department of Transportation and the City of Crestview. This diverse funding ensures the smooth progress of the project and the realization of its various components.In conclusion, the Southwest Crestview Bypass project is making remarkable progress. From the installation of the bridge infrastructure to the construction of the new school, every aspect is moving forward with determination. This project will have a significant impact on the region, improving connectivity and providing essential facilities for the community.