As of November 26th, 95% of the sheetrock has been completed, and the crews are approximately 60% finished with taping. This level of progress showcases the efficiency of the construction team. Additionally, 40% of the ceramic wall tile has been installed but awaits grouting. The painting of interior walls has also begun this week, starting with the mechanical and electrical rooms. Next week, the focus will shift to installing the mechanical and electrical finishes.
The installation of windows is expected to commence mid-next week and could take up to 1-2 weeks. This is an important step in completing the building and ensuring proper ventilation and natural light.
The exterior brick pavers have been installed, and 75% of the exterior siding is now complete. While the entire building is being worked on, the priority remains on finishing the liquor store portion first. The city has leased the Beaver House as a temporary liquor store and plans to move into the new space after the first of the year. Once the liquor store is ready, the rest of the building will follow suit.
City Administrator Mike Roth is finalizing the furniture selections for the city hall and shelving for the liquor store. As of November 26th, the cost of the selections is $160,000, with $175,000 set aside in the project budget. However, the chairs for the council chambers still need to be selected. There may be some fluctuations in the final cost, but Roth is confident in the overall plan.
Recently, John Haggenmiller installed a time capsule in the new building. Mayor Tracy Benson collected a variety of items to include, such as materials from the Grand Marais Public Library, a staff t-shirt from the Grand Marais Recreation Park, a 2025 calendar from photographer David Johnson, a book on the history of downtown Grand Marais, and other small items. This time capsule will serve as a memento of this important construction project.
The new city hall/liquor store building is expected to be completed in late January or early February. Stay tuned for more updates on this exciting construction project.
Beginning on Monday, December 2nd, contractors will commence the installation process. They will be focusing on installing sewer lines, storm drainage, curbing, and guttering. This work is essential for the proper functioning of the local area. To ensure the safety of pedestrians and motorists, detour routes will be established and clearly marked. These detour routes will guide people around the construction area, allowing them to continue with their daily activities without any major disruptions. The detour routes will be well-signposted, making it easy for people to find their way.
The installation process may take up to three weeks to complete. During this time, the local community is asked to be patient and follow the detour routes. The contractors will be working hard to complete the installation as quickly and efficiently as possible, minimizing any inconvenience to the community. Once the installation is complete, the local area will benefit from improved infrastructure and a more pleasant environment.
The OLLE Art Walk project is not just about improving infrastructure; it is also about enhancing the local community. The installation of sewer lines, storm drainage, curbing, and guttering will help to prevent flooding and improve the overall drainage system in the area. This will reduce the risk of property damage and make the local area more resilient in the face of heavy rain and storms. In addition, the improved infrastructure will also enhance the aesthetic appeal of the local area, making it a more pleasant place to live, work, and visit.
The OLLE Art Walk project is also part of a larger initiative to develop and improve the Hickory Trail. By improving the infrastructure along the trail, more people will be encouraged to explore and enjoy the natural beauty of the area. This will have a positive impact on the local economy, as more tourists and visitors will be attracted to the area. The improved infrastructure will also make it easier for local residents to access the trail and enjoy outdoor activities.
For more information regarding the OLLE Art Walk, visit hickorync.gov/olle-art-walk-information. This website will provide detailed information about the project, including the installation schedule, detour routes, and any other relevant information. To learn more about the entire Hickory Trail, visit www.hkytrail.com. This website will provide information about the trail, including its history, features, and activities. By visiting these websites, you can stay informed about the OLLE Art Walk and the Hickory Trail and make the most of these exciting projects.